Megawatt Data Centre

January 11, 2019

36MW project entice with 8000 over cabinet assembly with both Hot and Cold aisle with containment solution, data centre eccentric which was executed within 17 months, with dedicated 50 personnel whom carried out Project, Supervision and Handy Point Edge Service (HPES) rendered for on-time completion.

Solution and Expertise deployed:

  • Cable Containment Solution
    • 10,000 meters of cable containment units with accessories help increase safety and enhance installation flexibility
  • Hot Aisle & Cold Aisle Solution
  • Fibre termination of Ribbon fibre over 100,000 nodes
  • LAN point termination exceeding 50,000 nodes
  • Cabinet Installation over 8,000 units capacit

Duration for completion:

2013 ~ 2015